RFP QuestBeta
Awarded · ResultStage · contract

Braintree District Council

Maldon Prom Park Water Main

Construction MaterialsCPV 44161000
Value£50k
Awarded9 Aug 2015
Published19 Jun 2015
RegionEast of England
Outcome — awarded

This is a contract result notice, not an open opportunity. Details from the official award data.

Contract value in context
£50ktotal contract value
median £135k
this tender£0£4.1m

This sits in the lower-middle of the Construction Materials & Structures band — a mid-scale opportunity. Based on 10,341 valued Construction Materials & Structures tenders in our corpus.

The brief

Maldon District Council (MDC) has identified the need to improve the water supply to the Promenade Park.

Visitor numbers have greatly increased since the existing supply was installed, and this project will also ensure spare capacity for future projects.

Works will include but is not limited to – • Laying larger incoming water main • Reconfiguration of existing water supply network on the Park • Removal of redundant pipework • Installation of additional outlet points/features • Liaising with Statutory Undertaker to ensure work completed complies with relevant legislation Works must start after the closure of the Splash Park, during the first 2 weeks of September, exact date to be confirmed, and must be completed no later than 27 November 2015.

In order to ensure you receive all documents and clarifications, please can you send an email expressing an interest in this project to paula.jarvis@braintree.gov.uk Please send all clarification questions to paula.jarvis@braintree.gov.uk This Tender closes 12noon on Monday 10th August 2015 and all responses are to be returned using the address label supplied

Key requirements

What the supplier must deliver

01

Maldon District Council (MDC) has identified

Maldon District Council (MDC) has identified the need to improve the water supply to the Promenade Park.

02

Visitor numbers have greatly increased since

Visitor numbers have greatly increased since the existing supply was installed, and this project will also ensure spare capacity for future projects.

03

Reconfiguration of existing water supply network on

Reconfiguration of existing water supply network on the Park.

04

Liaising with Statutory Undertaker to ensure work

Liaising with Statutory Undertaker to ensure work completed complies with relevant legislation.

05

Works must start after the closure

Works must start after the closure of the Splash Park, during the first 2 weeks of September, exact date to be confirmed, and must be completed no later than 27 November 2015.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Braintree District Council, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
7de760c5-a471-4d75-9471-b5b95679f72b
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
MDC/2015/0005
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction Materials & Structures

Scroll to explore the market network

Braintree District Council’s tender network

Assembling the network…