RFP QuestBeta
ClosedStage · contract

Balfour Beatty VINCI Systra JV

Stamford Brook Sewer Diversion Works - Old Oak Common (S4) Station - HS2 Re-Issue

Construction MaterialsCPV 44130000 44163130 45232400
Value£5.0m
Deadline7 Feb 2020
Published24 Jan 2020
RegionLondon
Timeline
Published 24 Jan 2020ClosedCloses 7 Feb 2020
Contract value in context
£5.0mtotal contract value
median £135k
this tender£0£5.4m

This is a large award for Construction Materials & Structures — above three-quarters of comparable contracts. Based on 10,341 valued Construction Materials & Structures tenders in our corpus.

Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

If you have submitted a response to our previous advertisement, you do not need to respond to this advertisement as well.

Stamford Brook Sewer Diversion Diversion of the Stamford Brook Sewer at the Old Oak Common site, including the Micro Boring works under the Great West Main Line and North Pole Depot New 1200mm int. dia. sewer that runs within central box footprint, supported at ground level within a reinforced concrete trough (R.C Trough provided by others.

Construction of two deep manholes, including live connection to existing Thames Water 'egg' sewer.

New 1200mm int. dia. sewer that will be pipe jacked under the GWML tracks and North Pole Depot from a launch pit located within the Wormwood Scrubs to a receiving pit connecting the sewer to Phase 2.

Length of Pipe Jack 160m.

New 450mm internal diameter sewer running south westerly connecting new 1200m sewer to the existing Thames sewer (live connection at low flows).

Length of 450mm pipe run, 350m with association manhole chamber.

Logistic for material in and out of site constrained by access vi Braybrook Street.

Sub-contractor to be self-sufficient within Wormwood Scrubs providing all temp services, welfare, and security.

Sub-contractor to gain approval from Thames Water with regards construction methods and live connections at upstream and downstream locations.

Supply chain will need to demonstrate their specialist knowledge in: Thames Water Approved Contractor Status Micro Boring Expertise Deep Drainage Works Temporary Works Ability to competently work in the Railway environment Programme March 2020 commence detailed planning, SHEQ documentation approval with all parties, temporary works design and approvals, fabrication design and approvals.

Commence site clearance and site set up in July 2020 (post nesting season) Complete drainage and pipe jacking Sep 2020 to Jan 2021.

Feb 2020 commission live sewer.

Mar 2020 reinstate landscape and demobilise.

Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.

The exact scoring criteria are currently being developed by BBVS, and shortlisted suppliers will be invited to register for the ERP system in due course.

What is clear at this stage is that tenders will be scored competitively across a range of criteria, such as, but not limited to: Commercial, Programme, Methodology, HSEQ, Capability and Capacity.

In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Interchangeat Old Oak Common.

Key requirements

What the supplier must deliver

01

If you have submitted a response

If you have submitted a response to our previous advertisement, you do not need to respond to this advertisement as well.

02

Supply chain will need to demonstrate their

Supply chain will need to demonstrate their specialist knowledge in:.

03

Respondents to this opportunity should be advised

Respondents to this opportunity should be advised that shortlisted applicants will be invited to tender through an external ERP system.

04

In 2018, Balfour Beatty, VINCI and Systra

In 2018, Balfour Beatty, VINCI and Systra (BBVS) created a strategic alliance to deliver major infrastructure projects for HS2, in particular the Interchangeat Old Oak Common.

Derived from the notice text — always confirm against the original documents.

What this bid requires

Skills, tools & certifications

Detected from the notice — the capabilities and credentials this bid calls for. Click one to see who wins that work.

Buyer intelligence

Make the case to bid

Reveal who to approach at Balfour Beatty VINCI Systra JV, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
a6abe02a-e5fe-4f24-a439-d3bdaeaa57fe
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
C4N47638026
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction Materials & Structures

Assembling the market network…

Balfour Beatty VINCI Systra JV’s tender network

Assembling the network…

Also open now

Similar open tenders

Plant Room Replacement Works at Plas Bryn Extra Care, Cardiff

Codi Group Ltd

Closes 31 Jul 2026Construction
£180kValue

Property Works and Consultancy DPS

Thirteen Housing Group Limited

Closes 31 Aug 2030Agriculture
£15.0mValue