Design, construction and installation of new shop at Rievaulx Abbey - AWARD
This is a contract result notice, not an open opportunity. Details from the official award data.
This sits in the lower-middle of the Construction band — a mid-scale opportunity. Based on 64,002 valued Construction tenders in our corpus.
To design the shop layout within the brief given by English Heritage Contract Manager (Martin Wright), to manufacture off Site and install at Rievaulx Abbey between 16th May 2016 to 20th May (A maximum of 5 days installation allowed).
The following scope of work is included: • Work with main contractor at Site and the English Heritage Contract Manager, to ensure project delivered on time and within budget. • Design shop layout to brief, following English Heritage shop fit out policy • Attend design meetings and installation meetings as required. • Visit Site to take final measurements before manufacture – make any other site visits as required. • Provide samples of raw materials to be used to manufacture shop fit.
The finishes are set out in the pricing section of this document.
Sample and finishes board will be required. • Source and supply raw materials as specified for shop. • Manufacture of the counter and all units in retail shop, this includes the fitting of any in built directional lighting (LSD light bulbs to be used).
The counter to include 3 tills as shown on the plan and to allow for a CCTV monitor to be integrated and recessed into the desk (supplied and installed by the main contractor). • Although no electrical work is required, wall units and counter must have trunking and spur fittings installed ready for connection at Site. • Manufacture off Site and deliver to Site.
Note there are width restrictions on some roads leading to the site.
The price must include delivery to Site and vehicle restrictions accounted for. • Provide technical drawings for English Heritage M&E Maintenance and Electrical teams as required including counter layouts and unit layouts • Provide any other drawings as requested by English Heritage contract manager related to design of the shop and individual unit design • Install all shop units and counter to plans as agreed, this includes taking away any waste materials and packaging generated from the shop fit. • After 12 months identify and complete any snagging to the satisfaction of the English Heritage Contract Manager for sign off.
It will not include • Any alternations to buildings on Site • No electrical work on Site - connection of units and counter to site power will be completed by approved English Heritage contractors • No decoration work • No work to flooring
What the supplier must deliver
Work with main contractor at Site
Work with main contractor at Site and the English Heritage Contract Manager, to ensure project delivered on time and within budget.
Provide samples of raw materials to
Provide samples of raw materials to be used to manufacture shop fit.
Source and supply raw materials as specified
Source and supply raw materials as specified for shop.
The counter to include 3 tills as
The counter to include 3 tills as shown on the plan and to allow for a CCTV monitor to be integrated and recessed into the desk (supplied and installed by the main contractor).
Although no electrical work is required, wall
Although no electrical work is required, wall units and counter must have trunking and spur fittings installed ready for connection at Site.
Derived from the notice text — always confirm against the original documents.
Make the case to bid
Reveal who to approach at English Heritage-Retail , and generate a go-to-market strategy from their news, accounts and people.
Ask me about this tender, the buyer, who wins their work, or whether you should bid.
- OCID
- bf0c5870-456a-4b56-81a7-759449f79a6c
- Stage
- contract · Contract
- Source
- Contracts Finder
- Buyer ref
- P/REF 00000266 - AWARD
Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.
Who wins this kind of work
The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.
Top suppliers & buyers in Construction
English Heritage-Retail ’s tender network
Assembling the network…
Similar open tenders
Design and Installation of Photovoltaic and Battery Storage Systems at Various Educational Establishments
Blaenau Gwent County Borough Council
Construction of new 30 person boardroom at College of Policing site
COLLEGE OF POLICING LIMITED