RFP QuestBeta
ClosedStage · preprocurement

Network Rail Infrastructure Ltd

Remote Condition Monitoring for Track Buckle Risk and Detection

R&DCPV 73000000
ValueValue not published
Deadline14 Jan 2022
Published18 Nov 2022
RegionUK-wide
Timeline
Published 18 Nov 2022ClosedCloses 14 Jan 2022
Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

The onset of hot weather brings with it the risk of track buckling if high rail temperatures are combined with deficiencies within the track system (i.e., incorrect rail stress, disturbed / deficient ballast, lateral alignment faults, incorrect rail joint gaps, etc.).

Ideally, all such deficiencies should be eliminated before the hot weather season starts.

As air temperatures increase during periods of hot weather, rail temperatures also increase.

Metals expand and contract as the temperature changes.

If a length of steel rail is rigidly clamped at both ends and then heated, the metal expands and is put under compression until the force becomes too great and exceeds the track systems lateral resistance forces.

The purpose of this pre market activity is to engage with the market, both internal and external to the rail industry, to request information on existing and / or new technologies that have the capability of enabling remote monitoring of critical rail temperature sites (i.e., monitoring rail temperatures and abnormal lateral track displacement).

Network Rail would like to invite prospective suppliers to submit a maximum two-page summary of existing technologies or technology development / research ideas, which address this challenge statement.

Network Rail would also like to understand indicative costs in delivering a product trial.

Network Rail reserves the rights to hold discussions with Suppliers, following a response to this RFI.

Network Rail are committed to investing internal Research and Development funding to support this challenge statement in future stages.

To access the instruction and guidance on how to be apart of the initial Pre Market engagement and potential tender please follow the below steps to access the Pre Market engagement support document for Remote Conditioning Monitoring for Track Buckle Risk and Detection: 1.

Follow the link - https://networkrail.bravosolution.co.uk/web/login.html 2.

From the welcome screen, access the "View Current Opportunities" link and select "#26734 - Remote Condition Monitoring for Track Buckle Risk and Detection".

Should you wish to respond to this RFI, please follow the below instructions: 1.

Follow the link - https://networkrail.bravosolution.co.uk/web/login.html 2.

From the welcome screen, access the "View Current Opportunities" link and select "#26734 - Remote Condition Monitoring for Track Buckle Risk and Detection PIN R&D" 3.

Download the attachments- "Request for Information - Track Watchperson RCM" and "Appendix 1: NR/TA/SC/SP/0XX".

4.

Complete your 2-page summary including indicative costs for a trial of the solution.

5.

Please send your two-page summary document via email as attachments to Byron.Reilly@networkril.co.uk with the email subject "Project 26734 - Track Watchperson RCM".

The response deadline for this RFI is 17:00 on Friday 14th January 2022.

Key requirements

What the supplier must deliver

01

Ideally, all such deficiencies should be eliminated

Ideally, all such deficiencies should be eliminated before the hot weather season starts.

02

Network Rail are committed to investing internal

Network Rail are committed to investing internal Research and Development funding to support this challenge statement in future stages.

03

To access the instruction and guidance on

To access the instruction and guidance on how to be apart of the initial Pre Market engagement and potential tender please follow the below steps to access the Pre Market engagement support document for Remote Conditioning Monitoring for Track Buckle Risk and Detection:.

04

Should you wish to respond to this

Should you wish to respond to this RFI, please follow the below instructions:.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Network Rail Infrastructure Ltd, and generate a go-to-market strategy from their news, accounts and people.

Deep dive · beta

The full intelligence dossier

Our agent reads Network Rail Infrastructure Ltd’s accounts, hunts live signals, finds the people who decide — and hands you a bid strategy plus a go-to-market influence plan, including what your team should post this week. You approve every paid step.

Source & provenance
OCID
c705a29b-04fb-4c47-b5f5-5b6eafc2cc7d
Stage
preprocurement · Withdrawn
Source
Contracts Finder
Buyer ref
tender_294454/1028190
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Research & Development

Scroll to explore the market network

Network Rail Infrastructure Ltd’s tender network

Assembling the network…

Also open now

Similar open tenders

Nature-based interventions evidence review: ecosystem function, benefits, and nature-related risks

Natural England

Closes 17 Jul 2026R&D
£41kValue

DS51EES72026 - Monitoring and Evaluation - EDGE Punjab Project with UNICEF

British Council

Closes 20 Jul 2026R&D
£24kValue