RFP QuestBeta
ClosedStage · contract

Balfour Beatty VINCI Systra JV

Fit Out - WP12.9 bathroom IPS and Sanitaryware Fit Out - Old Oak Common (S4) Station

Construction MaterialsCPV 44211200 45431200 45421141 45431100
Value£1.0m
Deadline9 Aug 2024
Published10 Jul 2024
RegionLondon
Timeline
Published 10 Jul 2024ClosedCloses 9 Aug 2024
Contract value in context
£1.0mtotal contract value
median £135k
this tender£0£4.1m

This is a large award for Construction Materials & Structures — above three-quarters of comparable contracts. Based on 10,341 valued Construction Materials & Structures tenders in our corpus.

Match for your company
Sign up free to see how well this tender matches your company — the score, the signals that align, and where the gaps are.
The brief

WP12.9 - Bathroom IPS and Sanitaryware Fit-Out Scope of work: OOC HS2 Station Bathroom IPS and Sanitaryware Fit-Out Package (WP12.9) consists of the design, procurement, installation and assurance of Toilet IPS panelling, cubicle partitions, sanitaryware, tiling, furniture, fittings and equipment, to the bathroom facilities in the HS2 Station, the Great Western Main Line Station (GWML) and Shared Accommodation Building (SAB).

This includes individual rooms such as accessible toilets, as well as larger customer welfare facilities.

The scope of this package includes the following: • Design Development: Prepare the design for construction, manufacture/procurement and installation of Toilet IPS panelling, cubicle partitions, sanitaryware, wall tiling, furniture, fittings and equipment including detailed plans, elevations, general arrangements, and fabrication drawings.

These drawings should encompass all necessary interface and connection details, structural elements, ancillary elements and products to meet the prescribed performance requirements.

Additionally, the Subcontractor is required to coordination their works within walls and ceilings with the relevant interfacing contractors.

The Subcontractors design must take account of the requirements for firestopping measures for movement joints and cavities to meet the prescribed HS2 specifications and design assurance process. • Samples and Mock-Ups: Provide samples, visual mock-ups or benchmarks as deemed necessary, to ensure compliance with design and quality standards. • Material Supply and Installation: Supply all required materials, labour, supervision, plant, access means and equipment for the Bathroom IPS and Sanitaryware Fit-Out, in accordance with the approved design. • Assurance and Certification: Generate and supply comprehensive assurance documentation for all installations, including certifications from accredited installers.

This shall also include the testing and commissioning under a temporary or permanent power state for powered appliances such as hand dryers, sensor activated sanitaryware and equipment.

This documentation should encompass asset labelling, tagging, electrical safety certification and any fire related certification, to ensure compliance with Building Regulations Act (2010). • Coordination: Ensure coordination of IPS panelling and bathroom installations with various Subcontractors, MEPH and flooring installations with the HS2 OOC appointed MEPH and flooring and ceiling contractors.

The following optional scope of works may be applied to this package, depending on supply chain capabilities: • Staff accommodation kitchen fit-out. • Staff lounge fit-out. • Wall tiling.

Key requirements

What the supplier must deliver

01

These drawings should encompass all necessary interface

These drawings should encompass all necessary interface and connection details, structural elements, ancillary elements and products to meet the prescribed performance requirements.

02

Additionally, the Subcontractor is required to coordination

Additionally, the Subcontractor is required to coordination their works within walls and ceilings with the relevant interfacing contractors.

03

The Subcontractors design must take account

The Subcontractors design must take account of the requirements for firestopping measures for movement joints and cavities to meet the prescribed HS2 specifications and design assurance process.

04

Samples and Mock-Ups: Provide samples, visual mock-ups

Samples and Mock-Ups: Provide samples, visual mock-ups or benchmarks as deemed necessary, to ensure compliance with design and quality standards.

05

Material Supply and Installation: Supply all required

Material Supply and Installation: Supply all required materials, labour, supervision, plant, access means and equipment for the Bathroom IPS and Sanitaryware Fit-Out, in accordance with the approved design.

Derived from the notice text — always confirm against the original documents.

Buyer intelligence

Make the case to bid

Reveal who to approach at Balfour Beatty VINCI Systra JV, and generate a go-to-market strategy from their news, accounts and people.

Source & provenance
OCID
e000e0ae-86aa-4c27-bab0-524b392ae273
Stage
contract · Contract
Source
Contracts Finder
Buyer ref
C4N82278983
View the original notice on Contracts Finder

Contains public sector information licensed under the Open Government Licence v3.0. Source data © Crown copyright.

Market context

Who wins this kind of work

The suppliers and buyers around this opportunity — drawn from official award data. Drag to orbit; click a node to explore.

Top suppliers & buyers in Construction Materials & Structures

Assembling the market network…

Balfour Beatty VINCI Systra JV’s tender network

Assembling the network…

Also open now

Similar open tenders

Supply & Fit Mobile access gantries

Thameslink Southern Great Northern Limited (TSGN)

Closes 31 Aug 2026Construction Materials
£550kValue